Southern Company (SO): Vogtle Nuclear Project Q220 Quarterly Monitor

June 2020

Total Pages: 17

Table Of Contents

  • Vogtle Summary
  • Key Takeaways
  • GP Potential Cost Exposure
  • Cost & Schedule Analysis
  • EPC Contractor History
  • Concluding Thoughts
  • Disclosures

Regulatory Background: Vogtle is regulated by the Georgia Public Service Commission (GPSC). GPSC’s primary role is to protect rate payers & determine if project costs can be justifiably passed-through via utility rates. In the quarters that follow we’ll venture to aggregate, analyze, and interpret cost overruns through the lens of GPSC, to put together a thoughtful estimate of what cost overruns will eventually land with SO shareholders.

  • Quarterly Deep Dive Into Southern Company’s (SO) $27B Vogtle Nuclear Expansion. Southern Company (SO), is the largest owner of the Vogtle Nuclear Facility, via the 46% held by its wholly-owned subsidiary Georgia Power.
  • Vogtle has two active units (Units 1-2), which have been in-service since 1987-89. A two unit expansion (Units 3-4) was approved in 2009
  • Units 3 & 4 were originally expected to be in-service in 2016-17 and cost a combined ~$14B, the expansion project is now 6-7 years behind schedule, with costs rising to ~$27B….and potentially higher (slides 3-6).
  • Hence, the premise of adding a W|EPC Quarterly Vogtle Project Monitor to our Utility & Energy research platform: Digging into those cost overruns – particularly the bulging EPC costs, to get a more accurate and detailed view of the potential headwind for project stakeholders and SO shareholders.

Recently viewed reports

W|EPC: Gorgon LNG – Assessing Potential Operational Contributors To Kettle Cracks, Mid-October A More Likely Restart

Gorgon LNG – Pump The Breaks On Crack Narrative: While potential fabrication errors have been the primary narrative around the Propane Kettle cracks that shut down Gorgon LNG, it’s feasible that operational issues (and one in particular) may have contributed or even partially caused the cracks on Train-2’s kettles, which could have significant and more complex implications.

August 2020
$950